tesa Platinum Partner · Adhesive tape converting in Shenzhen

Payment Terms Risk Checklist: Nine Questions to Settle Before a First Tape Order

Nine questions on payment terms and risk before a first order with a tape supplier: entity, currency, milestone, documents, verification and change control.

Technical guides941 wordsUpdated 07 November 2026

Technical guidesPublished 07 November 2026Updated 07 November 2026

A first order goes wrong on payment when the entity, the currency, the trigger event or the document set was never written down, and nine questions below close those four gaps before money moves. Payment terms are the record those gaps get closed in, and a supplier who cannot answer them in writing has not priced a first order for anyone yet. Ask them of every tape supplier on your shortlist and require the answers in the same thread as the quotation; each item is what to ask, why it matters, and how we answer.

1. Which legal entity receives the payment?

Ask for the registered name on the bank account and compare it with the name on the proforma invoice and on the export documents. Why: a mismatch between paying and exporting entity stalls a shipment at destination customs, and it is how a fraudulent account swap gets past finance. Our answer: the receiving entity is stated on the invoice before any transfer, and the legal name we trade under is published on the company contact page.

2. Which currency, and who absorbs the movement?

Ask whether the quotation and the invoice carry the same currency, and what happens if the rate moves between the two dates. Why: an offer priced in one currency and invoiced in another transfers the exposure silently. Our answer: the invoice currency is confirmed at quotation and depends on your entity and currency; a quotation issued against a destination is re-confirmed rather than assumed.

3. What event releases the balance?

Ask the supplier to name the trigger in words: material committed, goods packed, goods passed inspection, ex-factory, or documents presented. Why: a milestone written as a date can be met by paperwork that your broker will not accept. Our answer: the payment structure is agreed per order and the milestone wording is written next to the Incoterm on the quotation, so the trigger and the responsibility boundary describe the same moment.

4. Which documents must exist before the balance is released?

Ask for the full document list, then check it against what your import broker requires. Why: paying against an incomplete set means paying twice, once to the supplier and once to a clearance agent. Our answer: commercial invoice, packing list, transport document and certificate of origin as applicable, plus TDS, MSDS, RoHS and REACH statements and a first-article report against the grade and drawing actually ordered; the quality page describes what those records contain.

5. How do you verify bank details before the first transfer?

Ask for a verification route that does not run through the email that carries the details. Why: business email compromise in this trade arrives as a corrected account number on a reissued proforma. Our answer: confirm the account against a phone number published on the supplier's own site, not one printed in the attachment, and expect a supplier to welcome the call-back rather than resent the delay.

6. What is the change-control rule if the entity or account changes?

Ask what evidence accompanies a change, and who has to sign it. Why: a rule that exists only after an incident is not a rule. Our answer: no bank-detail or entity change is acted on without an out-of-band confirmation to a previously verified contact, and we expect the same discipline from a buyer's side when a purchasing entity changes mid-order.

7. Who bears correspondent bank charges?

Ask which fees are deducted in transit and whether the supplier expects the invoice amount to arrive whole. Why: a short payment caused by chain fees reads as a partial payment and can hold a shipment. Our answer: charge allocation is stated at quotation with the currency and the entity, because the answer differs between a buyer paying from a Malaysian or Indonesian account and one paying through an intermediary.

8. Which Incoterm is on the invoice, and does the payment match it?

Ask for the term and check that the milestone sits on the right side of the boundary. Why: payment structured around a ship's rail on an EXW order describes an event nobody controls. Our answer: we quote EXW, FOB Shenzhen, CIF or DDP by agreement, and the destination-side terms are confirmed against the port or address you name on the quote request page before the invoice is issued.

9. What happens to money already paid when the specification changes?

Ask what portion of a payment is already converted into material, and what a later drawing revision costs and when it takes effect. Why: a change after material commitment is not a cancellation, and treating it as one starts the relationship with a dispute. Our answer: we state which portion was spent on committed stock and reissue the quotation for the changed specification, with timing depending on material availability, tooling and cutting route.

The document set to reconcile before paying

  • Proforma invoice with entity, currency and milestone wording
  • Commercial invoice and packing list matching the shipment
  • Transport document appropriate to the Incoterm
  • Certificate of origin where your clearance needs it
  • TDS, MSDS, RoHS and REACH statements for the ordered grade
  • First-article report and lot trace record

Reconcile all six against each other before approving the transfer; a discrepancy visible on paper costs a phone call, and the same discrepancy discovered at a port costs a demurrage invoice. Terms written before that reconciliation are cheap. Terms rewritten after it are not. Send your questions and your draft purchase order through the quote request page, or read the documentary answers on our general FAQ first.

Commercial and process terms on this page are the questions a converter has to answer, not a standing offer. Order quantities, lead times, tooling charges, sample terms, freight and payment structures are confirmed at quotation against your drawing, your material and your destination, and only figures already published elsewhere on this site are stated as commitments.

Technical guides

More in this section

All technical guides

Send the drawing, the material and the destination.

We answer on the specific construction: what we hold, what we slit or laminate, what the quantity and the terms look like for your job.